26/04/2018
QBC Mackay – following the opening of the new inbound bridge (constructed by QBC) over Vines Creek on Mackay-Slade Point Road in north Mackay, piling has commenced on the outbound bridge. With all driven piles already complete, works have progressed onto the bored pier piles.