Queensland Bridge & Civil
  • 2
  • 2
  • 2
  • 2
  • 2
  • 2
  • 2
  • 2

Project Value: $11.8M

Project Duration: 21 weeks

Client: Department of Transport and Main Roads

Project Overview

As a result of the major storm events throughout South East Queensland during and since January 2011, significant damage was incurred to the State's transport network. The Department of Transport and Main Roads has awarded the pavement improvements to the Cunningham Highway between Inglewood and Goondiwindi to QBC under the Transport Network Reconstruction Program (TNRP).

Project Characteristics

This project was over several sections along the Cunningham Highway totalling approximately 15km.

The project included;

  • Provision for Traffic;
  • General Earthworks;
  • Unbound granular pavement overlays;
  • In-situ stabilisation;
  • Asphalt works;
  • Bitumen primer seal and seal;
  • Culvert Works;
  • Road furniture.

Key Project Outcomes

Improved road pavement along the most effected sections of the Cunningham Highway which will increase pavement life, improve resistance to future flood damage and provide safe passage for motorists travelling between Inglewood and Goondiwindi.