Project Value: $5.0m

Duration: 26 weeks

Client: Moreton Bay Regional Council

Project Overview

This project involved the construction of a 3 span concrete pedestrian bridge, associated batter protection, concrete paving approaches, retaining walls, drainage, watermain relocation and lighting.

Project Characteristics

This contract includes;

  • Earthworks;
  • Drainage works;
  • Cast In-Situ Piles;
  • Pile cap construction;
  • Substructure construction;
  • Scour protection;
  • Precast concrete deck units supply and erection;
  • Cast In-situ concrete deck;
  • Bridge railings;
  • Retaining walls;
  • Approach works;
  • Lighting (D&C);
  • Landscaping.

Key Project Outcomes

This project now completed provides a safe, all weather pedestrian and bicyclist crossing point across the South Pine River near the existing road crossing.