Project Value: $1.6m
Project Duration: 26 weeks
Client: Ipswich City Council
Project Overview
The project involves the replacement of an old single lane timber bridge with a new 2 land single span concrete bridge, approach earthworks and roadworks. The site is on Hallett's Road over Six Mile Creek in Redbank Plains.
Project Characteristics
This contract includes;
- Traffic Management including road closure;
- Existing Bridge Demolition;
- Earthworks;
- Drainage culvert works;
- Pavement and Road Furniture;
- Bridgeworks;
- Retaining Walls;
- Asphalt and Bitumen Seal;
- Service and Electrical Works;
- Landscaping.
Key Project Outcomes
This new bridge will improve traffic flows through the local area and reduce the potential for accidents due to improved road geometry and a wider bridge. This project will also facilitate the safe movement of pedestrian traffic through the area.