Project Value: $19.2m

Project Duration: 35 weeks

Client: Scenic Rim Regional Council

Project Overview

This project involved the construction of 5 new concrete bridges and approaches plus the upgrade of a section of Beechmont Road near Canungra.

 

The locations of the five bridges are;

 

    1. Sharp Bridge, Beechmont Road - Ch 3250;
    2. Botan Creek Bridge, Beechmont Road - Ch 5460;
    3. Back Creek Bridge, Beechmont Road - Ch 14970;
    4. Bennett Bridge, Illinbah Road - Ch 680;
    5. Jerome Bridge, Upper Coomera Road - Ch. 3960.

With the section of Beechmont Road adjoining the approach works to Sharp Bridge.

 

 Project Characteristics

This contract included the following works; 

  • Traffic Management including side track construction;
  • Earthworks;
  • Bridge Construction including bored piles and precast deck units;
  • Drainage works;
  • Pavement and Road Furniture;
  • Asphalt and Bitumen Seal; 
  • Minor Landscaping.

Key Project Outcomes

This project has increased the flood immunity of all bridges, improved motorist and pedestrian safety and reduced maintenance costs to the Council.