Project Value: $8m
Duration: 30weeks
Client: Gladstone Regional Council
Project Overview
This project is for the replacement of 4 bridges (8 spans in total) and the upgrade of their approaches in the Lowmead and Miriam Vale areas.
Project Characteristics
This contract includes;
- Bored Piles;
- Precast Headstocks and Abutments;
- Precast Deck and kerb units;
- Transverse Stressing;
- Cast in-situ Kerbs;
- Earthworks;
- Roadworks;
- Existing Bridge Demolition.
Key Project Outcomes
This project will significantly improve the flood immunity and reduce maintenance costs for these bridges.