Project Value: $1.0M
Project Duration: 13 weeks
Client: Brisbane City Council
Project Overview
As a result of flood damage to the Bishop Street Footbridge Brisbane City Council have engaged QBC to replace the existing structure with a more flood resilient concrete structure.
Project Characteristics
The project will involve the construction of a 3 x 14m span concrete bridge complete with;
- Demolition of existing bridge;
- 8 x Bored piles;
- Concrete Abutment, Pier Headstock, Column and Pile Cap construction;
- Supply and erection of Precast Concrete Deck Units;
- Construction of a cast in-situ concrete deck;
- Supply and erection of pedestrian balustrade;
- Bridge Lighting.
Key Project Outcomes
To replace this vital piece of infrastructure with a more robust, flood resilient footbridge and return permanent access across Enoggera Creek to local residents.