Project Value: $5m
Project Duration: 36 weeks
Client: Department of Transport and Main Roads
Project Overview
This project is for the construction of noise barriers along Old Northern Road, between Hamilton Road and the Jinker Track, Albany Creek. In December 2014, the Department undertook additional noise monitoring along the project site on Old Northern Road. The results from the noise monitoring, along with community feedback and discussions with the Everton and Aspley Members of Parliament, helped the Department refine the design of the noise barrier project.
Project Characteristics
This contract includes;
- Earthworks;
- Pile for noise barrier wall;
- Concrete works;
- 2544m of 2m high noise barrier fencing.
Key Project Outcomes
The project will reduce road noise levels to a significant number of residents in the local area and improve their quality of life.