Project Value: $12.4m

Duration: 40weeks

Client: Lockyer Regional Regional Council

Project Overview

This project included the remediation of landslips at six locations on four separate roads within the Lockyer Valley region as a result of three major flood events from November 2021 until May 2022.

Project Characteristics 

Thicontract included landslip remediation works include soldier piles (cast in-situ piles), sheet piling, rock anchors, landscaping, roadworks, and road furniture on the following identified roads,

Berlin Road, Mount Berryman
East Egypt Road, Mount Whitestone
Robinson Road, Gatton
Mountain View Drive, Hatton Vale

 

Key Project Outcomes

This project has significantly improved the flood immunity and ensured these roads are open to residents and roadusers.